McCarren Park Soccer Field

McCarren Park Synthetic Turf Soccer Field Reconstruction

This project will reconstruct the existing multi-use synthetic turf field.

Project Timeline

Design
Start Date: May 2016
Projected Completion Date: December 2016
Completion Date: March 2017

Procurement
Start Date: March 2017
Projected Completion Date: December 2017

Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Funding
Total Funding: Between $3 million and $10 million
Funding Source: Mayoral

Keep up on the process.

McCarren Park Hawk

McCarren Park’s Insta-Famous Hipster Hawk

Greenpointers

If you’re like many of us, you’ve probably seen a hip-looking hawk roaming about McCarren Park. Whether he’s sunbathing on a Pendleton blanket with a Turkey’s Nest Margarita or simply strutting around the farmers’ market sporting his newest pair of Raybans, this hawk is LIT. And how he has an Instagram account. Check it out.

McCarren Hipster Hawk Instagram